>
Climax Molybdenum Company, a subsidiary of Phelps Dodge Corporation with corporate headquarters in Phoenix, Arizona, owns the Henderson
Mine. Phelps Dodge is one of the largest mining companies in the world, and is primarily engaged in the production of copper and molybdenum
from large open pit mines. The Henderson mine, which produces molybdenum ore by an underground mining method known as panel caving,
is the company's only underground operation. Molybdenum is a grayish colored metal that is mainly used to produce high strength alloy
steels. Other uses include chemicals and lubricants, and as lament supports in light bulbs. The mine site is located 80.5 km (50 mi)
west of Denver, Colorado and lies 3170 m (10,400 ft) above sea level on the eastern side of the Continental Divide. It can easily
be reached from Denver International Airport (DIA) by taking Interstate 70 west to the Empire exit, Highway 40 approximately 16 km
(10 mi) to the bottom of Berthoud Pass, and continuing approximately 3 km (2 mi) on the well maintained mine access road. The entire
trip from DIA can be made in approximately 1.5 hours. The mine site is within Clear Creek County and is surrounded by the Arapaho
National Forest. The approximately 11.7 km2 (2900 acre) of land containing the Henderson orebody, located underneath Red Mountain,
is entirely privately owned by Climax Molybdenum Company. Additionally, the 52- km2 (12,800 acre) mill site located near Kremmling
Colorado is also entirely owned by the company. The mine is currently producing about 21,000 tons of raw ore per day. It is estimated
that the mine has adequate reserves for about twenty more years of production. Upon closure of the Henderson Mine, the company plans
to re-open the Climax Molybdenum Mine located near Leadville, Colorado.
Geologic Setting:
The Henderson deposit is composed of two partially
overlapping ore bodies that lie 1,080 m (3550 ft) beneath the summit of Red Mountain. The ore bodies are entirely within a Tertiary
rhyolite porphyry intrusive complex that has intruded the Precambrian Silver Plume granite. The deposit is elliptical in plan, with
overall dimensions of 670 m by 910 m (2200 ft by 3000 ft), with an average thickness of 185 m (600 ft). The top of the deposit is
at an elevation of 2610 m (8560 ft), while the lower limits range from 2,340 m (7680 ft) on the west to 2,100 m (6900 ft) on the east.
The mineralization is relatively continuous in the ore bodies and consists of molybdenite and quartz in random intersecting closely
spaced veinlets. The general nature of the orebody and the surrounding host rock is that of very competent (high strength) granite
with compressive strengths ranging from 100 to 275 Mpa (14,500 to 40,000 psi). Host rock areas that have very little molybdenite have
been found to behave appropriately for medium-strength granite. The proposed UNO facilities will be located under Harrison Mountain,
which is situated just to the west of Red mountain (Figure 8). Regional geologic studies have indicated the Harrison Mountain area
to be barren of mineral deposits, and for this reason extensive exploration drilling has not been performed. The Henderson Geology
Staff_ carried out detailed surface mapping of Harrison Mountain in the early 1980's. This mapping revealed highly competent Precambrian
Silver Plume Granite along the crest of the mountain, and on the northeast and southeast-facing slopes. Broad zones, up to 300 m (1000
ft) wide of northeast-trending broken and fractured granite were mapped along the upper northwest slopes below the ridgeline. This
broken zone lies within the overall trend of the Vasquez Pass Shear Zone. The downward extent of this broken zone is not known. It
does, however, project to the northwest of the proposed UNO excavation, one mile below the peak. The only exploratory drill hole located
on Harrison Mountain was CX-126, drilled in 1968 from an elevation of 3502 m (11,489 ft) on the southeastern slope. The hole was drilled
from an access road below the saddle that separates Harrison from Red Mountain, and is above the trace of the proposed access tunnels
on 7500 Level. The vast majority of the core was in Precambrian Silver Plume Granite, with minor intervals of Idaho Springs Schist
that occur as inclusions. What is noteworthy in this hole is that the Silver Plume Granite becomes more competent with depth, beginning
at around 2957 m (9,700 ft) in elevation. Rock competencies range between 6 to 8 (with 9 being maximum). The contact between Silver
Plume and Urad Porphyry is at an elevation of 2654 m (8706 ft), with rock competencies remaining high to the end of the hole at an
elevation of 2294 m (7526 ft). The bottom of this hole is very close to the 9HW-99LD intersection on 7500 Level. This intersection
is the preferred location of a 600 m (2,000 ft) exploration drill hole to the west under Harrison Mountain. Diamond drill holes to
the north of CX -126 corroborate the high rock competencies seen in that drill hole. Drill holes CX-135 and CX-103 both show high
competencies in the Silver Plume Granite and in the Urad Porphyry. Silver Plume Granite has historically been a competent unit during
underground development at the Henderson Mine. On the 7500 Level, the Granite remained competent in 9A and 9HW drifts. Based on the
detailed geologic logs from surface exploration diamond drill holes and the information gathered by mining through the Precambrian
units on the 7500 Level, the proposed large UNO excavation under Harrison Mountain should be in competent Precambrian Silver Plume
Granite. Exploratory drill holes from the 7500 Level will be necessary to verify this conclusion.
Mine Description:
The mine began operation
in 1976 after a 10-year redevelopment program and a $500 million investment. The Henderson 2000 modernization program, which consisted
of the new underground crusher room excavation, conveyor transfer station excavation and conveyor decline, was begun in 1996 and was
completed in 1999. From the beginning, the mine was designed as a high capacity operation, and the mine infrastructure is engineered
to support production in excess of 30,000 tons per day, which equates to about 10 million tons per year, easily making the Henderson
Mine one of the 10 largest underground mines in the world today. The mine is accessed from the surface by an 8.53 m (28 foot) diameter
men and material shaft that extends down to the 7500 level. The shaft cages can transport up to 200 people at a time, and the trip
from the surface to the 7500 level takes about 5 minutes. The cage can accommodate loads with maximum dimensions 2.6 m wide, 7.1 m
long, and 3.9 m high (8'-7"w _ 23'-5"l _ 12'-11"h) weighing up to 30 tons. Taller items up to 5 m in height (16' 4") can fit on the
cage if they are small enough to fit in one corner. Loads of up to 50 tons can be carried if a crosshead is substituted for the cage
and counterweights used. An inter-level ramp with a grade of about 7% extends from the 7500 level down to the 7065 truck level. From
the 7700 production level, ore is transported with large capacity Load Haul Dump units 831 (LHDs) with capacities of about 10 tons
per scoop, to bored 2.5 m diameter ore passes that extend vertically down to the 7065 truck level. On the 7065 truck level, ore is
loaded from large ore chutes at the bottom of the ore passes into 80 ton side dump underground haul trucks, (the largest underground
trucks manufactured), which haul the ore to the underground crusher. The crusher reduces the size of the ore to pieces 8 inches or
less, and has a capacity of 2300 tons per hour. From the bottom of the crusher below the 7065 level, the ore is loaded on to the first
of three conveyor belts, PC1, which transports the ore 1.6 km (1 mi) to the PC1/ PC2 transfer station located at the 7500 level. At
the transfer station, the ore is then loaded onto the PC2 underground conveyor, and is transported 16.1 km (10 mi) under the continental
divide to the PC2/PC3 transfer station. PC2 is the longest single flight conveyor in the world. At the PC2/PC3 transfer station the
ore is loaded onto the 6.4 km (4 mi) long PC3 overland conveyor that transports the ore to stockpiles for subsequent processing at
the mills. The entire journey from the bottom of the crusher to the mill stockpile takes about 2 hours. Mill tailings are placed in
large containment areas that will be reclaimed and re-vegetated when the mine is closed. The operating permit allows for the deposition
of in excess of 340 million tons of mill tailings. From 1976 through 1991, approximately 98 million tons of ore were produced from
the 8100 level. In 1992, the 7700 level was brought into production and over 70 million tones have been produced from this level so
far. The next production level will be at the 7210 level, located 149 m 849 below the 7700 level. Ventilation to the production level
is supplied by a multi horizon level 15 to 20 m (50 to 65 ft) below. Both intake and exhaust air are transported on two horizons to
provide a general north-to-south fresh air-to-exhaust airflow. Each production ore pass is connected to exhaust air and has an associated
intake raise from the intake drifts. This entire level is connected to an 8.5-m (28-ft) intake shaft and to 7- and 10-m (23- and 33-ft)
exhaust shafts by way of several 5- by 5-m (16- by 16 ft) ventilation drifts. Approximately 3.2 million cubic meters per hour (1.9
million cfm) of air is moved through the mine. Mine water is treated at the Urad Water Treatment Plant, which was built in 1996 with
a $9.8 million capital investment. The plant is capable of treating 15 m3/m (4000 gpm) using a two-stage lime precipitation process
for removal of manganese, zinc, aluminum, and other metals. The treated mine water is discharged into Clear Creek and used by various
communities down stream. The Henderson Mine is the second largest consumer of electricity in Colorado. Two permanent substations are
integrated into the statewide electricity distribution network as shown on Figure 10: Large mining equipment used at the Henderson
mine include 10 ton capacity Load Haul Dump units (LHD) and 80 ton capacity side dump underground haul trucks.
Two MSHA approved emergency
escape routes for the safe evacuation of mine personnel in the event of a mine emergency exist. The primary escape way is Number 2
Shaft, and the secondary escape way is through the PC2 tunnel. The largest excavations in the mine were constructed as part of the
Henderson 2000 project. These were the PC1/PC2 transfer station, 12.8 m wide _ 27.5 m long _ 17.7 m high (42 ft _ 90 ft _ 58 ft) constructed
in Silver Plume Granite, and the underground crusher station 18.6 m wide _ 28.3 m long _ 14.6 m high (61 ft _ 93 ft _ 48 ft), constructed
in the Vasquez Porphyry rock type.
Two MSHA approved emergency escape routes for the safe evacuation of mine personnel in the event
of a mine emergency exist. The primary escape way is Number 2 Shaft, and the secondary escape way is through the PC2 tunnel.
A summary
of other mine infrastructure that exists as well as what would be available to the various projects is given below.
Mine ventilation:
The mine ventilation system has a capacity of 1,900,000 cubic feet per minute (cfm) provided through three large surface fans. Of
this total amount, about 200,000 cfm in excess capacity would be available to UNO, which is significantly more than the estimated
50,000 cfm that would be required to ventilate the large UNO room and access tunnels.
Electricity:
Two 24 MW transformers for a total
of 48 MW are available at the mine site. The mine is currently using 10 MW, but also requires an additional 10 MW for backup. With
the existing transformer stations, UNO would have 14 MW available with 14 Megawatt for backup. The electrical network has 100% redundant
feed from the power company, Xcel Energy, from the Cabin Creek substation near Georgetown and Blue River substation located between
Kremmling and Silverthorne.
Mine dewatering: The mine pumping and dewatering system has a capacity of 5000 gpm. the mine is currently
using about 1000 gpm.
Water treatment:
The surface water treatment facility has a capacity of 4000 gpm. The mine is currently using
about 1100 gpm normally and about 2000 gpm during spring runo_, leaving about 2000 gpm available.
Compressed air: There are two 8000
cfm, one 6000 cfm, and one 1700 cfm compressors available as part of the mine compressed air system. The mine currently uses about
6000 cfm, leaving in excess of 16000 cfm available.
Concrete batch plant:
A concrete batch plant for mixing concrete and shotcrete
that would be required during construction is available. The batch plant has a capacity of 200 yd3 per day, of which the mine is currently
using about 60 yd3 per day. About 140 yd3 per day would be available.
Rock conveyor system: The mine conveyor system for rock removal
was designed for a capacity of 40,000 tons per day. The mine is currently using about 21,000 tons per day. The estimated maximum that
would be required for mine production is 30,000 tons per day, leaving at least 10,000 tons per day available.
Outreach facilities:
An area at the mine site about 4 acres in size is available for the con- struction of outreach facilities.
Summary:
Considering only
the primary factors such as geology, cost, quality, environmental impact, the Henderson Mine is a very strong competitor for siting
UNO and other underground science experiments. When other important factors such as cooperation from mine ownership, accessibility,
proximity to industry, technicians, and major academic institutions, are included, Henderson becomes the preferred choice for UNO.
As a potential national facility, when such additional factors as quality of life, educational, recreational, and cultural amenities
are also considered, Henderson offers a very attractive package. With a minimum 5,000' overburden at the proposed UNO excavation cavity,
the Henderson Mine is deep enough to meet the low cosmic ray background levels required for UNO and most other proposed underground
experiments. Deeper levels are readily achievable at relatively low cost. Preliminary estimates suggest that levels at 7,000' can
be reached with primary and secondary tunnels in less than a year for around $20M. Preliminary geological studies indicate that the
rock at the proposed excavation site is likely to be Silver Plume granite, ideally suited to large cavity excavation. Funding has
been secured to verify this by performing a core-drilling. As a recently upgraded modern mine, Henderson is safe and has the infrastructure
and excess capacity to accommodate easily the additional excavation and infrastructure support required for the UNO experiment. Its
main shaft is large enough (28' diameter) to accommodate sea containers, and it has in place the necessary excess electrical power
and water treatment capacity to meet the needs of an underground laboratory. Furthermore, the efficiencies of its high capacity excavation
and rock removal methods will save tens of millions of dollars in excavation costs. It is also important to note that the environmental
impact is fully accommodated within Henderson's existing permits. When the mine ceases operations (estimated between 15-25 years),
the conveyer tunnel will provide a convenient high capacity horizontal access as well. All the major local stake holders are very
supportive of this project. Of particular importance is Phelps-Dodge, the parent company of the Climax Molybdenum Henderson Mine.
They own not only the mining operations but all the land involved in the project. They have been fully cooperative and supportive,
providing access to mine documents such as sites plans, environmental impact reports, radon levels, ventilation capacity etc. Though
the legal relationship between the company and a national facility would need to be defined in detail, they have expressed a great
willingness to pursue the initiative.
It is remarkable that, as one of the ten largest underground operating mines in the world, the
Henderson Mine is located within minutes of an interstate highway and just an hour's drive from a major metropolitan area with its
broad supporting base of technical industries, highly trained workforce, research universities, and a major international airport
- not to mention four professional sports franchises. It is worth mentioning as well that seven major mountain and ski resorts are
located within an hour of the mine.
Henderson Mine provides an historically unique opportunity for the nation to create - at relatively
modest cost and in a highly desirable location - the major underground facility needed to address some of the deepest questions of
contemporary physics.
Henderson Mine, Empire Colorado
Written by Colorado School of Mines - Golden, Colorado 3/12/2004 and published here with their permission.
Introduction:
The
Henderson mine, located near Empire, Colorado, is situated in a stunningly beautiful area surrounded by snow-capped peaks and outdoor
recreation facilities in Colorado's Rocky Mountains.
The Arapaho Project Inc.
Why the Henderson Mine in Colorado?